Field Testing / Commissioning Solution






Field testing is the stage where electrical equipment moves from an installed asset to an operating asset. Factory test reports can confirm that a transformer, switchgear panel, cable, circuit breaker, or protection relay met its factory requirements. They cannot confirm that the equipment arrived at site without damage, was installed correctly, was wired according to the drawings, and will operate correctly as part of the complete electrical system.
This is where field testing and commissioning become critical.
From the UHV perspective, field testing is not simply a matter of taking measurements on individual devices. The test plan has to follow the actual site sequence:
Installation → Inspection → Individual Equipment Testing → System Testing → Protection Testing → Energization → Functional Verification → Commissioning
UHV field testing solutions are applicable to:
Substations
Power Plants
Renewable Energy Plants
Industrial Facilities
Data Centers
Railway Power Systems
Oil & Gas Facilities
Mining Projects
Manufacturing Plants
Grid Connection Projects
Transformer Stations
MV/HV Cable Systems
GIS/AIS Switchgear Systems
The equipment scope can cover:
Transformer Testing · Cable Testing · GIS Testing · Circuit Breaker Testing · CT/PT Testing · Relay Protection Testing · Insulation Testing · Partial Discharge Testing · AC Withstand Testing · Battery Testing · Grounding Testing
1. Testing Background
A field commissioning project has one fundamental difference from laboratory testing: the test environment is the actual operating site.
The equipment may be located inside a substation, outdoors in a solar plant, inside an industrial facility, underground in a cable trench, or installed in a compact GIS room. Temperature, humidity, electromagnetic interference, access conditions, auxiliary power, grounding, and site safety all affect the test.
A typical commissioning project contains several layers.
Equipment Layer
Individual equipment is checked first:
- Transformer
- GIS
- Switchgear
- Circuit Breaker
- Cable
- CT/PT
- Motor
- Generator
- Battery
Protection Layer
The protection and control circuits are then checked:
- Protection Relay
- Trip Circuit
- Closing Circuit
- Alarm
- Interlocking
- Measurement
- Communication
System Layer
The complete electrical system is finally verified:
Transformer → Switchgear → Cable → Load
or:
Generation → Transformer → Substation → Grid
This sequence matters because a system can contain individually qualified components but still fail during commissioning because of an incorrect cable connection, CT polarity, phase sequence, relay setting, grounding connection, or trip circuit.
UHV's field testing approach therefore focuses on test sequence, equipment compatibility, field conditions, measurement reliability, and complete documentation.
2. Testing Objects








2.1 Power Transformers
Field transformer testing may include:
- Transformer Turns Ratio
- Winding Resistance
- Insulation Resistance
- Tan Delta
- Excitation Current
- Transformer Oil BDV
- Partial Discharge
- AC Withstand where required
The field results should be compared with factory test data and previous maintenance records where available.
2.2 GIS and AIS
GIS/AIS commissioning can involve:
- Insulation Resistance
- AC Withstand
- Partial Discharge
- Contact Resistance
- Circuit Breaker Timing
- SF6 Gas Quality
- Dew Point
- Gas Leakage
- Interlocking
For GIS, the quality of assembly and cleanliness can have a direct effect on insulation performance.
2.3 Circuit Breakers
Field testing evaluates both the electrical contacts and operating mechanism.
Typical measurements:
- Opening Time
- Closing Time
- Travel
- Speed
- Coil Current
- Contact Resistance
- Phase Synchronization
- Operating Sequence
2.4 MV/HV Cables
Cable commissioning is particularly important after installation and termination.
Typical tests include:
- Insulation Resistance
- Sheath Testing
- VLF Testing
- AC Hipot
- AC Resonance
- Partial Discharge
- Cable Fault Location
The test method should match the cable type, voltage level, insulation system, cable length, and project specification.
2.5 CT/PT
Field CT/PT testing verifies the actual installed measurement and protection circuits.
Typical tests include:
- Ratio
- Polarity
- Excitation
- Burden
- Accuracy
- Winding Resistance
- Insulation
- Knee Point for applicable CTs
2.6 Protection Relays
Commissioning tests may include:
- Overcurrent
- Earth Fault
- Differential
- Overvoltage
- Undervoltage
- Overfrequency
- Underfrequency
- Directional
- Distance where applicable
- Motor Protection
- Transformer Protection
The final test should verify the relay together with the trip circuit and circuit breaker.
2.7 Batteries and DC Systems
Substation batteries provide power for protection and control during abnormal conditions.
- Testing may cover:
- Battery Voltage
- Cell Voltage
- Internal Resistance
- Capacity
- Discharge
- Charger
- DC Insulation
2.8 Grounding Systems
- Field grounding tests can include:
- Ground Resistance
- Ground Grid
- Grounding Continuity
- Equipment Bonding
- Step Voltage
- Touch Voltage
Large substations and industrial facilities should be evaluated as complete grounding networks.
3. Testing Requirements
The field testing plan should be prepared before equipment arrives on site.
UHV recommends confirming the following information first:
Electrical Parameters
- System Voltage
- Rated Current
- Frequency
- Short-Circuit Level
- Transformer Capacity
- Cable Voltage
- Cable Length
- Cable Capacitance
Equipment Information
- Transformer Type
- GIS/AIS Type
- Circuit Breaker Type
- CT/PT Specifications
- Cable Type
- Motor/Generator Ratings
- Battery Voltage
Project Information
- Single-Line Diagram
- Equipment Layout
- Cable Schedule
- Protection Drawings
- Control Wiring
- Grounding Drawing
- Factory Test Reports
- Previous Test Records
Testing Requirements
- Required Test Items
- Test Voltage
- Test Duration
- Test Frequency
- Acceptance Criteria
- Applicable Standards
- Site Safety Requirements
This information determines whether a compact portable tester is sufficient or whether the project requires a larger high-voltage test system.
4. Testing Methods
4.1 Visual & Mechanical Inspection
Before electrical testing begins, the installation should be inspected.
Typical checks include:
- Equipment condition
- Nameplate data
- Terminal connections
- Cable terminations
- Grounding connections
- Mechanical assembly
- Oil level
- GIS gas condition
- Circuit breaker mechanism
- Control wiring
This stage can prevent incorrect energization and unnecessary test failures.
4.2 Insulation Resistance Testing
Insulation resistance testing is commonly used for:
- Transformers
- Cables
- Motors
- Generators
- Switchgear
- Auxiliary systems
The test provides an initial assessment of insulation condition before higher-voltage testing.
4.3 AC Withstand Testing
AC withstand testing verifies dielectric strength under specified test conditions.
Typical field applications include:
- GIS
- Switchgear
- Transformers
- Cables
- Motors
- Generators
When the test object has substantial capacitance, an AC Resonant Test System can be considered.
For system selection, UHV evaluates:
Required Test Voltage + Test Object Capacitance + Test Frequency + Test Duration
rather than selecting a system from voltage rating alone.
4.4 VLF Testing
VLF testing is widely used for specified medium-voltage cable field testing.
It is particularly useful where cable capacitance makes conventional power-frequency testing difficult to perform with a practical field setup.
Important parameters include:
- Cable Voltage
- Cable Length
- Cable Capacitance
- VLF Test Voltage
- Test Frequency
- Test Duration
4.5 AC Resonance Testing
AC Resonance is used when the test object presents a relatively high capacitive load.
Typical applications include:
- HV Cables
- GIS
- Large Electrical Equipment
The resonant circuit allows the test system to generate the required AC voltage without requiring the same apparent power as a conventional direct AC source.
4.6 Partial Discharge Testing
PD testing is used to identify localized insulation activity.
Potential defects include:
- Internal Voids
- Surface Defects
- Floating Particles
- Poor Insulation Interfaces
- Cable Accessory Defects
- Transformer Insulation Problems
- Field PD testing requires attention to:
- Background Noise
- Sensor Selection
- Grounding
- Shielding
- Test Connections
- Signal Separation
Industrial sites can contain strong interference from drives, motors, switching devices, communication equipment, and other electrical systems.
4.7 Transformer Testing
A typical field sequence is:
TTR
→ Winding Resistance
→ Insulation Resistance
→ Tan Delta
→ Excitation Current
→ Oil BDV
→ PD where required
The sequence can be adjusted according to equipment condition and project specifications.
4.8 Circuit Breaker Testing
Circuit breaker analyzers measure:
- Opening Time
- Closing Time
- Pole Synchronization
- Travel
- Speed
- Coil Current
- Contact Resistance
These measurements provide both electrical and mechanical information.
4.9 CT/PT Testing
CT/PT field testing confirms that the installed device and wiring correspond to the protection and metering design.
Typical sequence:
Ratio → Polarity → Excitation → Burden → Accuracy → Insulation
For protection CTs, knee-point and saturation characteristics may also need to be verified.
4.10 Relay Protection Testing
Secondary injection testing provides controlled current and voltage signals to the relay.
The commissioning sequence verifies:
Input → Pickup → Timing → Logic → Output → Trip
The final functional test should confirm that the actual circuit breaker responds correctly to the protection output.
4.11 Grounding Testing
Grounding testing may include:
- Earth Resistance
- Ground Grid Resistance
- Continuity
- Bonding
- Step Voltage
- Touch Voltage
The test method depends on the grounding system design and project requirements.
5. Recommended Equipment
|
Field Testing Requirement |
UHV Equipment |
Typical Application |
|
Transformer |
Transformer Comprehensive Tester |
Transformer commissioning |
|
Transformer |
TTR Tester |
Ratio testing |
|
Transformer |
Winding Resistance Tester |
Winding testing |
|
Transformer |
Tan Delta Tester |
Insulation condition |
|
Transformer |
Oil BDV Tester |
Oil dielectric strength |
|
Cable |
VLF Hipot Tester |
MV cable |
|
Cable |
AC Hipot Tester |
AC withstand |
|
Cable |
AC Resonant Test System |
HV cable |
|
Cable |
Cable PD System |
Cable diagnostics |
|
Cable |
Cable Fault Locator |
Fault location |
|
GIS |
AC Resonant Test System |
AC withstand |
|
GIS |
PD Test System |
Partial discharge |
|
GIS |
SF6 Analyzer |
Gas purity |
|
Breaker |
Circuit Breaker Analyzer |
Timing/travel |
|
Breaker |
Contact Resistance Tester |
Contact resistance |
|
CT/PT |
CT/PT Analyzer |
Ratio/polarity |
|
Protection |
Relay Protection Test Set |
Relay commissioning |
|
Battery |
Battery Discharge Tester |
Battery capacity |
|
Grounding |
Ground Resistance Tester |
Ground system |
For large EPC commissioning projects, UHV can combine multiple instruments into a field testing package rather than treating every test as a separate procurement item.
6. Testing Procedure
Step 1 - Site Preparation
Before testing:
- Confirm equipment isolation
- Confirm safety boundaries
- Check grounding
- Verify auxiliary power
- Review test points
- Confirm calibration status
- Prepare test cables
- Confirm communication with the site commissioning team
High-voltage testing should only proceed after the site safety and isolation conditions have been confirmed.
Step 2 - Documentation Check
Compare:
Nameplate → Drawing → Factory Report → Actual Installation
Any discrepancy should be resolved before electrical testing.
Step 3 - Individual Equipment Testing
Typical sequence:
Transformer
Ratio → Resistance → Insulation → Tan Delta → Excitation → Oil → PD
Cable
Insulation → Sheath → VLF / AC → PD
Circuit Breaker
Contact Resistance → Timing → Travel → Coil Current
CT/PT
Ratio → Polarity → Excitation → Burden → Accuracy
Step 4 - Secondary Circuit Testing
Verify:
- CT circuits
- PT circuits
- Relay wiring
- Trip circuits
- Closing circuits
- Alarm circuits
- Interlocking
- Remote signals
Step 5 - Protection Testing
Test each protection function individually, then verify the complete trip logic.
For example:
Fault Simulation → Relay Pickup → Trip Output → Circuit Breaker Opening → Alarm
Step 6 - System Testing
After individual equipment tests are completed, verify the electrical system as a whole.
Examples:
Transformer → MV Switchgear → Cable → Motor
or:
Generator → Transformer → GIS → Grid
Step 7 - Energization
Energization should follow the approved commissioning sequence.
Typical stages:
Auxiliary Power
→ Control Power
→ Protection
→ Main Equipment
→ Busbar
→ Transformer
→ Outgoing Feeders
→ Load
Step 8 - Functional Verification
After energization, confirm:
- Voltage
- Current
- Phase Sequence
- Protection
- Metering
- Alarms
- Interlocking
- Communication
- Remote Control
- Equipment Operating Status
Step 9 - Commissioning Documentation
The final field report should normally include:
- Equipment Identification
- Test Date
- Test Instrument
- Instrument Serial Number
- Calibration Information
- Test Conditions
- Test Parameters
- Test Results
- Acceptance Criteria
- Test Engineer
- Customer Witness
- Final Conclusion
7. Applicable Standards
Field testing and commissioning may reference different standards depending on the equipment and project.
Common standards include:
IEC 60076 - Power Transformers
IEC 62271 Series - High-Voltage Switchgear
IEC 60255 Series - Measuring Relays and Protection Equipment
IEC 60034 Series - Rotating Electrical Machines
IEC 60840 - High-Voltage Cables
IEC 62067 - Extra-High-Voltage Cables
IEC 61936 - Power Installations Exceeding 1 kV AC
Depending on the project, additional requirements may come from:
- IEEE Standards
- Local Electrical Codes
- Utility Specifications
- Grid Codes
- Equipment Manufacturer Instructions
- EPC Commissioning Specifications
- Owner's Testing Procedures
The acceptance criteria should always be established from the applicable project documents rather than applying a generic value to every installation.
8. Test Parameters
Field testing requires accurate information about the test object.
|
Test Object |
Key Parameters |
|
Transformer |
Voltage, capacity, ratio, winding resistance |
|
Cable |
Voltage, length, capacitance, insulation type |
|
GIS |
Voltage, capacitance, gas pressure, test voltage |
|
Circuit Breaker |
Current, voltage, opening/closing time, travel |
|
CT |
Ratio, burden, knee point, excitation |
|
PT |
Ratio, burden, accuracy |
|
Relay |
Current, voltage, frequency, phase angle |
|
Motor |
Voltage, power, current, insulation |
|
Generator |
Voltage, capacity, winding configuration |
|
Battery |
Voltage, capacity, discharge current |
|
Grounding |
Resistance, continuity, step/touch voltage |
Most Important Data for Cable Testing
For UHV VLF or AC Resonance selection:
- Cable Rated Voltage
- Cable Length
- Cable Capacitance
- Required Test Voltage
- Required Test Frequency
- Test Duration
Most Important Data for AC Resonance
The required test system is primarily determined by:
Test Voltage + Capacitance + Frequency
For long cable systems, the cable capacitance is particularly important.
9. Common Testing Problems
Equipment Cannot Be Energized
Possible causes:
- Control wiring error
- Interlocking condition
- Protection lockout
- Incorrect auxiliary power
- Grounding problem
The commissioning team should trace the complete control path rather than repeatedly attempting energization.
Cable Test Failure
Potential causes include:
- Damaged insulation
- Poor termination
- Moisture
- Installation damage
- Incorrect test connection
- Incorrect test configuration
High PD Background
Common sources include:
- VFDs
- Motors
- Switching equipment
- Communication systems
- Poor grounding
- Nearby energized equipment
Field PD testing should begin with background measurement before interpreting the test object signal.
Abnormal Circuit Breaker Timing
Possible causes:
- Mechanism wear
- Coil problems
- Lubrication issues
- Control circuit problems
- Mechanical adjustment
CT Polarity Error
A polarity error can affect differential and directional protection.
The CT should therefore be verified before the relay functional test.
Protection Relay Does Not Trip the Breaker
The relay itself may be functioning correctly while the problem is located in:
Relay Output → Trip Circuit → Trip Coil → Breaker Mechanism
The commissioning test should therefore follow the complete path.
Inconsistent Test Results
Field conditions can change test results.
Possible causes:
- Temperature
- Humidity
- Grounding
- Test lead connection
- Electromagnetic interference
- Equipment temperature
- Previous test condition
Test conditions should be recorded with the measurement.
10. Equipment Selection Guide
Substation Commissioning
Recommended UHV package:
- Transformer Tester
- AC Resonant Test System
- PD Test System
- Circuit Breaker Analyzer
- CT/PT Analyzer
- Relay Protection Tester
- Ground Resistance Tester
- Battery Discharge Tester
Renewable Energy Commissioning
For solar and wind projects:
- Transformer Tester
- VLF Cable Tester
- AC Resonant Test System
- Cable PD System
- Circuit Breaker Analyzer
- CT/PT Analyzer
- Relay Protection Tester
- Grounding Tester
Industrial Plant Commissioning
Recommended scope:
- Transformer Testing
- Switchgear Testing
- Cable Testing
- Motor Testing
- Protection Testing
- Grounding Testing
- Battery Testing
GIS Commissioning
Typical equipment:
- AC Resonant Test System
- Partial Discharge Test System
- Circuit Breaker Analyzer
- Contact Resistance Tester
- SF6 Gas Analyzer
- SF6 Dew Point Meter
EPC Contractor
For EPC contractors, portability becomes important.
Consider:
- Equipment Weight
- Test Voltage
- Output Capacity
- Number of Test Modules
- Field Transportation
- Power Supply
- Environmental Rating
- Data Recording
- Software
- Calibration
- Local Service
UHV can configure the equipment according to the actual commissioning schedule and site conditions.
11. Case Studies
Case Study 1 - Substation Field Commissioning
A new substation is ready for energization.
UHV field testing equipment is used for:
Transformer
→ TTR
→ Winding Resistance
→ Insulation
→ Tan Delta
GIS
→ Contact Resistance
→ Circuit Breaker Timing
→ AC Withstand
→ PD
Protection
→ CT/PT
→ Relay
→ Trip Circuit
Grounding
→ Ground Resistance
→ Continuity
The final stage verifies the complete protection and energization sequence.
Case Study 2 - Renewable Energy Grid Connection
A large solar project needs to connect its collector system to the grid.
The commissioning scope includes:
- Transformer Testing
- MV Cable VLF Testing
- Cable PD Testing
- Switchgear Testing
- Circuit Breaker Timing
- CT/PT Testing
- Relay Protection Testing
- Grounding Testing
The equipment selection is based on the collector cable voltage, length, capacitance, transformer rating, and grid connection requirements.
Case Study 3 - Industrial Plant Commissioning
A new industrial plant contains multiple MV transformers, large motors, switchgear, and long cable circuits.
UHV's testing scope covers:
Transformer → Switchgear → Cable → Motor → Protection → Grounding
The field team verifies each stage before proceeding to the next energization stage.
Case Study 4 - Existing Substation Maintenance
An operating substation requires scheduled maintenance.
The testing program includes:
- Transformer Winding Resistance
- Tan Delta
- Circuit Breaker Timing
- Contact Resistance
- CT/PT Testing
- Relay Testing
- Battery Discharge
Ground Resistance
Historical data is used alongside current measurements to identify changes in equipment condition.
12. FAQ
Q: What Is Field Electrical Testing?
A: Field testing verifies the condition, installation, wiring, insulation, operation, and protection functions of electrical equipment after it has been installed at the actual project site.
Q: What Is The Difference Between Field Testing And Commissioning?
A: Field testing focuses on measurements and equipment verification. Commissioning goes one step further by verifying the complete electrical system and its operating sequence.
Q: What Equipment Is Normally Required For Substation Commissioning?
A: A typical package includes:
Transformer Tester
Circuit Breaker Analyzer
CT/PT Analyzer
Relay Protection Tester
AC Resonant Test System
PD Test System
Battery Tester
Ground Resistance Tester
The actual package depends on the substation configuration.
Q: Can UHV Provide Field Testing Equipment For EPC Projects?
A: Yes. UHV can configure portable testing equipment according to the EPC project's test scope, voltage levels, equipment ratings, standards, and site conditions.
Q: What Information Is Required Before Selecting The Equipment?
A: The most useful information includes:
Single-line diagram
Equipment list
Voltage levels
Transformer ratings
Cable lengths
Cable capacitance
GIS parameters
Circuit breaker data
CT/PT specifications
Protection functions
Grounding design
Required standards
Q: Is AC Resonance Suitable For Field Testing?
A: Yes. AC Resonance is commonly considered when the test object has significant capacitance, especially long HV cable systems and certain large electrical equipment.
Q: What Is Tested Before Energization?
A: Depending on the project:
Insulation
AC Withstand
Cable Sheath
Transformer
Circuit Breaker
CT/PT
Protection
Grounding
Battery
Control Circuits
Q: Can PD Testing Be Performed On Site?
A: Yes. Field PD testing is possible, but background noise, grounding, sensor configuration, and site operating conditions must be considered carefully.
Q: How Should Field Test Results Be Documented?
A: A professional test report should identify the equipment, test instrument, test conditions, test parameters, measured results, acceptance criteria, and responsible personnel.
Q: Can UHV Provide A Complete Commissioning Solution?
A: Yes. UHV can combine multiple testing systems into a project-specific field commissioning package.
13. Related Products
Transformer Testing
- Transformer Turns Ratio Tester
- Winding Resistance Tester
- Insulation Resistance Tester
- Tan Delta Tester
- Transformer Oil BDV Tester
- Transformer Comprehensive Tester
Cable Testing
- VLF Hipot Tester
- AC Hipot Tester
- AC Resonant Test System
- Cable Sheath Tester
- Cable Partial Discharge Tester
- Cable Fault Locator
GIS / Switchgear Testing
- AC Resonant Test System
- Partial Discharge Test System
- SF6 Gas Analyzer
- SF6 Dew Point Meter
- Contact Resistance Tester
Circuit Breaker Testing
- Circuit Breaker Analyzer
- Contact Resistance Tester
- Dynamic Resistance Tester
CT/PT Testing
- CT/PT Analyzer
- CT Analyzer
- PT Analyzer
- CT Excitation Tester
Protection Testing
- Relay Protection Test Set
- Three-Phase Relay Tester
- Secondary Injection Test System
Battery Testing
- Battery Discharge Tester
- Battery Capacity Tester
- Battery Internal Resistance Tester
Grounding Testing
- Ground Resistance Tester
- Ground Grid Tester
- Earth Resistance Tester
- Grounding Continuity Tester
14. Request a Quote
UHV Field Testing & Commissioning Solution
Field commissioning requires more than a collection of test instruments.
The equipment needs to match the project sequence, site environment, test object, electrical rating, and acceptance requirements.
UHV can configure a field testing package around:
- Transformer
- GIS / AIS
- Circuit Breaker
- Cable
- CT / PT
- Protection
- Motor / Generator
- Battery
- Grounding
- Grid Connection
Project Information to Send UHV
Project Type
→ Substation / Power Plant / Renewable Energy / Industrial / Railway / Data Center / Other
System Voltage
Installed Capacity
Transformer Rating
Cable Voltage
Cable Length
Cable Capacitance
GIS/AIS Type
Circuit Breaker Type
CT/PT Parameters
Protection Functions
Motor / Generator Ratings
Battery Voltage & Capacity
Grounding System
Required Test Items
Applicable Standards
Testing Location
Commissioning Schedule
UHV Field Testing Scope
Transformer Testing
Cable Testing
GIS Testing
Circuit Breaker Testing
CT/PT Testing
Relay Protection Testing
Insulation Testing
Partial Discharge Testing
AC Withstand Testing
VLF Testing
AC Resonant Testing
Battery Testing
Grounding Testing
Cable Fault Location
For a project-specific field commissioning package, UHV recommends sending the single-line diagram, equipment list, cable schedule, transformer data, GIS and breaker specifications, CT/PT information, protection configuration, grounding drawings, and required testing standards.
With these parameters, UHV can determine the appropriate test voltage, output capacity, test frequency, measurement range, portable configuration, and equipment combination for the actual field application.
Request a Field Testing / Commissioning Solution from UHV and let the test equipment configuration follow the electrical system-not the other way around.