Precautions For Safety Testing Of Series Resonance Testing System

Sep 05, 2025 Leave a message

Wuhan UHV specializes in producing series resonance (also known as power frequency AC withstand voltage test equipment). Next, we will share with you the precautions for safety testing of series resonance testing systems.

 

15


1. The circuit connection of the testing equipment must be accurate and reliable. High voltage equipment should be ensured to meet effective safety intervals. Before starting the test, a safety check must be conducted before powering on.


2. The tested product and testing equipment should be properly grounded. All equipment insulators must have sufficient insulation and mechanical strength.


3. After completing other testing projects, the AC withstand voltage test should be conducted with caution and there should be no insulation defects or doubts; If other testing projects are completed and insulation defects are suspected in the testing equipment, the AC withstand voltage test should not be started lightly to prevent unnecessary damage to the equipment. Before and after the communication withstand voltage test, the insulation resistance of the equipment should be shaken.


4. The surface of the tested product should be clean and dry. The installation conditions should be consistent with the actual usage situation. For oil filled equipment, the insulation oil should be stopped first before conducting voltage testing.


5. Before closing, check if the voltage regulating transformer is in the zero position. During the process of increasing and decreasing the voltage of the regulating transformer, the appearance should be monitored; During the process of applying voltage, the high-voltage circuit should be closely monitored to monitor whether the test object has noise.


6. In terms of ceramic insulation and switchgear, the boosting speed of voltage regulating transformers may be irregular; However, large equipment such as transformers and generators can be tested normally before the test voltage reaches 40%. When exceeding this voltage, it is necessary to uniformly increase the experimental voltage by about 25%/s.


7. The testing circuit should have appropriate protective facilities. If the experiment is conducted abnormally, the voltage should be reduced first, then the power supply should be disconnected, and the grounding wire should be checked again.


8. The duration of the AC withstand voltage test is generally 1 minute; If it is an insulating rod, equipment for live working, or organic insulation materials that exist separately, they should be kept for 5 minutes. After disconnecting the power supply, it must be grounded immediately. After ensuring safety, check if the test object is hot.


The purpose of using a series resonance tester for AC withstand voltage testing is to ensure the safe operation of power systems and equipment, and to avoid power outages and accidents. In actual communication withstand voltage testing, attention should also be paid to the safety of the testing process to ensure safe and smooth testing. Reliable grounding, good insulation, constant safety awareness, safe testing, and greater safety.